04/02/2020
6:43 AM
Tuolumne County Building and Safety Division
Inspections and Results
 
Permit No. B2018-00949 Permit Type   NEW SFD Site Address   9322 MONTEZUMA ROAD
JAMESTOWN, CA 95327
Applied   07/13/2018 Applicant   RADETICH CONSTRUCTION
Approved   12/28/2018 Owner   KEEFE, BRADLEY G TR
Issued   01/28/2019 Contractor   RADETICH CONSTRUCTION
Parent Permit No.   Description   SINGLE FAMILY RESIDENCE
  Notes  
 
  Date of Inspection Inspection Type Inspector Result Remarks Notes

 02/01/2019TEMP POWERDan CoughlinAPPROVED200 O H.

 06/26/2019SLABSLonnie McCartyAPPROVED(6/26/2019 11:01 AM LM) @ front porch Nailing of shear @ front porch bottom plate OK

 06/28/2019TRENCHLonnie McCartyAPPROVEDGate code 0717(6/28/2019 12:48 PM LM) electrical & water trench

 05/08/2019FOUNDATIONRick BarrieauCORRECTIONSPM 352-4176(5/8/2019 10:54 AM RB) Foundation inspection. 1) Follow detail given by Reuben @ Land and Structure. Get same detail stamped and approved by engineer. Rebar spacing is wrong and stem-wall too high. 2) All footings need to be dug 12 inches into undisturbed soil.-Particularly, the west end of house. 3) Many piers are undersized. 4) Provide compaction report for soil imported to site. WORK NOT READY------ Re-inspection fee due.

 05/10/2019REINSPECTIONDan CoughlinAPPROVEDSEE NOTES(5/10/2019 10:55 AM DANC) 1. Install concrete wash out prior to pour. No further inspections without.

 05/17/2019FOUNDATIONLonnie McCartyCANCELLED(5/17/2019 8:17 AM LM) foundation on garage Canceled on site Steel in dirt, mud and water in footings

 05/21/2019FOUNDATIONLonnie McCartyAPPROVEDAM 352-4176(5/21/2019 11:25 AM LM) garage foundation & slab

 06/04/2019SEWER CONNECTIONKatelyn OgburnCORRECTIONSAM 352-4176(6/4/2019 11:26 AM KO) 1. Fix 2 leaks. One at end of line and another at joint about 20' from end. 2. Will need clean fill for backfill of trench.

 06/06/2019REINSPECTIONDan CoughlinAPPROVEDSeptic connection 352-4176

 09/11/2019ROOF SHEATHINGLonnie McCartyCORRECTIONS352-4176(9/11/2019 4:05 PM LM) Roof & shear not ready, I asked the contractor to go through the plans details and shear schedule to assure that all details have been addressed.

 09/25/2019ROOF SHEATHINGLonnie McCartyCORRECTIONS652-4176(9/25/2019 1:58 PM LM) Roof & Shear 1. Provide 4" nailing on all C shear walls. 2. See shear wall schedule for all anchor bolt spacing 2 per plate and within 12" of plate break. 3. Pop all shiners in roof & walls and re-nail. 4. Wall line E calls for 16, of shear, you currently have 13'. 5. Provide 6" nailing on all B shear walls. 6. Complete blocking and strapping @ B perforated shear wall, wall line D. 7. Provide nailing from bottom plate to top plate on double studs @ HD's. 8. Stitch nail all double studs per plans. 9. Add missing SWSB 12X10 raked walls, wall line 1. 10. Add missing HD on B shear wall, wall line B. 11. Tighten all HD nuts. 12. Complete 4" nailing on E shear wall. 13. Add missing MSTC 66 straps @ E shear wall. We will look @ 2 side of shear wall E after frame inspection. 14. Provide 3X plates and blocks @ shear wall E. 15. Provide 2 bolts on each side of spandrel beams @ deck. 16. See shear wall schedule for anchor bolt spacing @ shear walls and underfloor area. 17. See detail 33/13 for A35 spacing @ gable end walls. 18. See plans for A35 spacing on wall line B. 19. Add blocks between trusses for perimeter nailing of roof sheathing @ california fill. 20. Install missing DSCZ-SDS3 @ wall lines B & 2, circled on plans. 21. See detail 25/13 for diagonal bracing @ gable end walls. 22. Install H-1 @ covered porch area. 23. See detail 27/13 for LSTA 18 straps @ front porch from rafter to rafter. 24. See page 9 for A35 spacing from truss to top plate, circled on plans. 25. See detail 20/13 for blocking @ joists parallel to walls, 48" oc. 26. Provide squash blocks through floor @ all HD's. 27. See detail 31/13 for continuous wall sheathing @ gable end walls. 28. Provide continuous wall sheathing all the way up @ balloon framed wall. 29. Block and nail plywood rips less than 24" on roof. 30. Provide 6" edge nailing & 12" field nailing on roof sheathing. 31. Complete nailing on gable end shear w

 09/30/2019ROOF SHEATHINGLonnie McCartyAPPROVEDRolled 9/27 352-4176(9/30/2019 12:44 PM LM) Roof sheathing only items 23, 29, 30, 32 have been addressed.

 10/23/2019SHEAR/BRACINGDan CoughlinAPPROVEDrolled 10/23 352-4176

 01/21/2020FRAMEDan CoughlinCORRECTIONSR PM 404-8679(1/21/2020 1:26 PM DANC) 1. Install water heater flue and TPR valve termination to exterior. 2. Have County approved sprinkler plan on site. 3. Add GFCI outlet at second sink in master bath. 4. Cover HVAC return plenum openings in hallway. 5. Strap ABS at mid stud bays. 6. Complete fire blocking at stud bays above fireplace.

 02/20/2020INSULATION WALLSLonnie McCartyAPPROVEDPM 404-8679(2/20/2020 12:58 PM LM) ceiling & floor

 02/07/2020FRAMEDan CoughlinAPPROVEDpm please