  Date of Inspection Inspection Type Inspector Result Remarks Notes

 06/04/2021FOUNDATIONLonnie McCartyAPPROVEDAM(6/4/2021 9:03 AM LM) piers @ front and back porch

 05/10/2021UNDERFLOOR PLUMBKatelyn OgburnAPPROVED W/COND484-0304(5/10/2021 10:16 AM KO) Setbacks OK Underslab plumbing was covered prior to inspection. Plumbing is under test and dry at building drain line stub out. Call for foundation inspection when ready.

 05/12/2021FOUNDATIONKatelyn OgburnCORRECTIONS484-0304(5/12/2021 11:00 AM KO) 1. Install 2 missing Hold Downs per plans at wall line B near wall line 1 (back right corner). 2. If using UFER for grounding electrode conductor, install 20' piece of #4 rebar running along bottom of footing and turning up near future electrical panel. Call for re-inspection or submit photos to Katelyn, 209-770-0042 with permit # in text. (5/18/2021 10:45 AM KO) #1 OK (5/19/2021 10:21 AM KO) UFER installed, #2

 06/03/2021FOUNDATIONRick BarrieauCORRECTIONSREBAR 484-0304 jamestwn(6/3/2021 9:52 AM RB) 1) Place steel matts in the piers with 3 inch clearance from bottom. 2) Slab steel to be supported with dobies. Steel to be in the middle third of slab thickness.

 07/12/2021ROOF SHEATHINGLonnie McCartyAPPROVEDSHEAR 484-0304

 07/21/2021FRAMELonnie McCartyCANCELLED(7/21/2021 10:19 AM LM) not ready

 07/28/2021FRAMEKatelyn OgburnCORRECTIONS& ROUGH ELEC 484-6268(7/28/2021 10:59 AM KO) 1. Ground all metal boxes. 2. Attic access to have a 21 1/2 x 30 x 30 clearance. Protect wires within 6 feet of attic access. 3. Install 2 missing nail plates, one by HD next to window on right side and one at back left corner, marked with X on studs. 4. Tie grounds in all boxes. 5. Complete installation of bathroom exhaust fan. 6. Secure shower valve. Check panel makeup at Future inspection.

 07/30/2021FRAMELonnie McCartyAPPROVED(7/30/2021 9:10 AM LM) frame, electrical, plumbing, hvac

 08/16/2021SHEETROCK NAILKatelyn OgburnAPPROVED

 09/27/2021FINALLonnie McCartyCANCELLED(9/27/2021 10:14 AM LM) Canc on site, not ready for final

 10/01/2021FINALLonnie McCartyAPPROVEDPM

 08/16/2021STUCCO LATHKatelyn OgburnAPPROVED

 07/02/2021ROOF NAILKatelyn OgburnCANCELLEDpls call 1st 484-0304(7/2/2021 1:25 PM KO) not ready for a complete inspection. Spoke with owner: - Nailing needs to be 6 inches on the edges and 12 inches in the field or better. Add missing nails. - Install AB at 48" OC per plans and at plate breaks. Tighten bolts. - Complete installation of missing top portion of Hold Downs on left and front of structure - Install missing clips - Add straps at patio cover connection to house per plans. - Provide WUI compliant eaves and venting by Final

 07/19/2021FRAMELonnie McCartyCANCELLED